Processing kilometers of cables on board


April 2020

Due to the COVID-19 pandemic all employees of Damen Shipyards Galati, including all subcontractors, are working in shifts to ensure a safe working environment. While this is challenging, good progress is still being made on board.

The erection of Wolfe Islander IV is completed! All sections have been successfully coupled. Inside the vessel most major equipment has been installed and outfitting works have started. The work include HVAC, piping, insulation and the pulling of no less than 90 kilometers of cable onboard the Damen Road Ferry 9819 E3.

Local dry stone walls as inspiration for interior design


April 2020

Due to the COVID-19 pandemic all employees of Damen Shipyards Galati, including all subcontractors, are working in shifts to ensure a safe working environment. While this is challenging, good progress is still being made on board.

Currently the Amherst Islander II is almost technically completed and her modern interior is very close to completion. The well trained eye will notice the ‘dry stone’ feature walls in the passenger areas. These feature walls are made from photos of the actual Amherst Island dry stone walls, captured by a local citizen.

Construction of "Wolfe Islander IV" is progressing well


March 2020

The construction of Wolfe Islander IV inside and out is progressing well.

Very recently the (backup) generator is installed on board. Check out the photos to see this is a big job and precision work!

Interior work is progressing at "Amherst Islander II"


March 2020

Despite the Coronavirus we’re happy that the yard in Galati is still able to continue with the Ontario road ferries.

The interior work is progressing at Amherst Islander II. Here’s a glimpse of the outside interior. Once the entire interior is finished completely we’ll show you more.

Welcoming of main switchboards on board


March 2020

While daily Class inspection on board the Wolfe Islander IV are witnessed closely by the Owner (ref. photo 1), also the main switchboards have been placed on board.

With a weight of almost 10MT tons each, you can imagine this is a serious operation (ref. photo 2)!

Visitors from Transport Canada


March 2020

Transport Canada visited the Amherst Islander II in order to review the vessel in accordance with the Canadian regulations. This must be done before the vessel arrives in Canada.

"Wolfe Islander IV" is progressing in dry dock


February 2020

While the assembling work of Wolfe Islander IV in dry dock is continuing well, a number of functional rooms is ready to be painted.

Take a look at the production photos and see the progress of the superstructure under construction as well.

Commissioning of "Amherst Islander II"


February 2020

Amherst Islander II is becoming more and more “green” as battery room 1 is provided with batteries now!

Lots of commissioning work like cable pulling, making connections, providing insulation are on the planning.

The wall - and ceiling installation work is progressing as well as functional tests of systems including the testing of the thrusters.

Good progress of "Wolfe Islander IV"

Great view on the working ground of the "Amherst Islander II"

Assembly of "Wolfe Islander IV" in drydock


December 2019

All parts of the ship hull are gathered in the dry dock for assembly. Not only the hull is taking shape, but also the passenger area above the car deck is under construction already.

The final shape of the Wolfe Islander IV is looming at the yard in Galati!

Outfitting "Amherst Islander II"


December 2019

While the Amherst Islander II is already in the water, the employees of Damen Shipyards Galati and subcontractors are working hard to commission the vessel.

One by one all systems on board are being put into service, until the moment she will sail on her own power for the first time.

Progress of "Wolfe Islander IV"


November 2019

While the Amherst Islander II is launched on 14. November, the 99-metres long Wolfe Islander IV is currently under construction in the dry docks. The launching ceremony for this Damen Road Ferry 9819 E3 is scheduled for mid-2020.

Check out the photos to view the progress of Wolfe Islander IV.

Launching of "Amherst Islander II"


November 2019

On the 14th of November the Amherst Islander II, a Damen Road Ferry 6819 E3, was launched at Damen Shipyards Galati in Romania. The ceremony was attended by representatives of the owner, the Ministry of Transportation Ontario, Canada, as well as Damen personnel. Check out the visuals to get an impression of the launching ceremony.

Outfitting blocks for "Wolfe Islander IV"


October 2019

The construction of Wolfe Islander IV is based upon large 'blocks' which are completely outfitted and painted in a controlled environment, before being assembled in the dry dock.

In total the complete vessel, up to main deck, contains of eight (8) of these massive outfitted blocks. Some weighing up to 56 MT each due to the Ice Class 1B hull!

It’s the passengers, stupid!


September 2019

Damen has come up with a way to ensure its public transportation vessels are tailored to hit the right spot for those travelling on them. Find out more here.

Abstract from the presentation “It’s the passengers, stupid” by Henk Grunstra at the Canadian Ferries Association (CFA) in Saint John, New Brunswick 2019

The keel laying for Road Ferry 9819 E3 is a fact!


September 2019

Under the watchful eye of the owner’s representative the official keel laying for the Wolfe Islander IV took place on Friday the 30th of August, 2019.

The local surveyors of Classification Society Bureau Veritas have handed over the corresponding certificate.

The construction of the sections for the Wolfe Islander IV is in full progress as there are at the moment already 15 sections, or more than 400 Tons of steel, in production.

Good progress of "Amherst Islander II"


August 2019

Under the clear blue skies of Galati, the yard is making good progress on the Amherst Islander II. She has completed her assembly on the slipway and the finalizing of the systems on board is now underway. The first of more than 70 kilometres of cable have been pulled and her fully-redundant dual main switchboards have been installed. The preparations for her final colour scheme are currently take place and before too long the Amherst Islander II will be seen in her full glory. Check out the photos to get an overall impression of this modern vessel.

"Amherst Islander II" close to its final form


July 2019

After the erection of all block sections of the vessel, the process of coupling these sections has started on the slipway!

The sections are already pre-outfitted and painting has already started.

The upcoming period the vessel will be fully assembled until the Amherst Islander II will take her final form.

"Wolfe Islander IV": the first major milestone - the cutting of the first steel!


June 2019

On the 10th of June 2019 the construction of the Wolfe Islander IV started by achieving the first major milestone: the cutting of the first steel!

This 98-meter road ferry will have the capacity to transport 399 passengers and 80 cars (or 40 cars+4 trucks) and will be operational in Ontario, Canada, between Kingston and Wolfe Island.
The vessel has the ability to sail fully electric and is therefore executed with a large battery capacity on board and shore based systems which allow the vessel to recharge during loading/unloading.
The new vessel will be delivered late 2020 ex. Yard.

"Amherst Islander II" takes shape!


June 2019

All sections of the hull have been erected and painting has started.
Shortly Damen Shipyards Galati will start connecting the ‘ring sections’ and then the vessel really takes shape.

"Wolfe Islander IV" and "Amherst Islander II" well on track


April 2019

It’s been a very busy and productive week in both Gorinchem and Kolham. Primary focus of this visit was the sign off on the final design elements for the Wolfe Islander IV; however we also met with subcontractors for our charging units and our electrical designers to see progress on our switching gear too. The Amherst Islander II construction is moving along as scheduled, with the Wolfe Islander IV steel cutting to commence in just a few weeks.

Miniature Road Ferry of first cut steel


March 2019

According to the tradition, the client receives a piece of the first steel cutting.

For this occasion, these miniature profiles of the road ferries are made especially for MTO in memory of the start of building their electric vessels, to begin with the Damen Road Ferry 6819 E3.

In the meantime, the yard is taking major steps in putting together sections up to the main deck.

Keel laying for Damen Road Ferry 6819 E3


January 2019

For the Damen Road Ferry 6819 E3 project the year 2018 ended successfully by achieving another major milestone. At the 20th of December 2018 the vessel’s keel was laid at the Damen Galati premises. In the presence of local representatives and Classification Society Bureau Veritas.

The Damen Road Ferry 6819 E3 is a modern ferry which will operate on electrical power and has the ability to sail as a hybrid. The new vessel is part of a large shore infrastructure renewal program which is carried out under the management of the owner, featuring the built of new docks provided with automated mooring and charging systems at each quay.

The vessel will be assembled and launched on the slipway of Damen Galati Hull Division I.

Start cutting for Damen Road Ferry 6819 E3


December 2018

The first important milestone of YN 539317, Damen Road Ferry 6819 E3 - start cutting - successfully took place at Damen Shipyard Galati on the 3rd of December.

The ferry, with a length of 71.70 meters, width of 19.80 meters and ice class 1B will replace Frontenac II, the 56-years-old ferry currently operating on Amherst Island route.

As the first electric operating vessel in the North America region & first ferry renewal program in 40+ years, YN 6819 has the following technical features:

Route: 3.8 km
Cruise speed: 9.0 kts
Contract speed: 11.8 kts
Operation: 20.5 hr/day (365 days)
Temp. range: +30 up to -25 degree (harsh winter conditions!)
Endurance: 5 days (hybrid)
Ice conditions: Moderate 1st year fresh water ice (1B)
Charging: Every time the vessel docks (approx. 40 times per day!)

The next milestone, keel-laying, is scheduled for the 21st of December 2018.

The official start of the project


November 2018

Exciting times for the Ministry of Transportation of Ontario. Last week the official start of the project has been announced at Damen Shipyard Galati, Romania. Upcoming Monday the 3rd of December, the first steel for the new Amherst Island ferry will be cut. “This is a major milestone for the project, all developments for these innovative electric ferries falls together now”, thus Jurriaan Jellema (project manager, Damen Shipyards Group). The Detailed Engineering of the Amherst Island ferry will be finalised early next year.

On the photo: Jurriaan Jellema (Project manager, Damen Shipyards Group)

Canadian Ferry Associations’ conference


October 2018

The first images of the new ferries for Amherst Island and Wolfe Island were presented at the Canadian Ferry Associations’ annual conference in Whistler last Tuesday October 3. Stuart Jones (the Ministry of Transport Ontario) and Leo Postma (Damen Shipyards) jointly presented the project of the two new ferries for an audience of more than 250 Canadian ferry professionals. They outlined the all-electric propulsion, project back ground and successful cooperation, all vital for achieving future proof innovative solutions.